The foundation is all prepped and ready for the steel delivery that is expected by the end of the week.

Tuesday, March 16, 2010


The sun is shinning as construction continues. The foundation and footings for the new meeting rooms are complete! We are just waiting for the steel delivery, which is now expected next week. Along with the foundation work... the new fire exit ramp that will be between the City Center and the Hotel has seen some major progress as well as some of the electrical systems inside the building.

Monday, March 1, 2010

finally some snow

While the snow that we finally got last week was good for winter sports tourism... it was not so good for City Center Construction. Construction took a small break while it snowed over a foot, and then rained even more, but we are back in full construction mode this week!

But despite the bad weather and the construction the annual Home Show was well attended!

Monday, February 22, 2010

Steel??

Not much updating has happened in the last month, but rest assured work has been moving forward. The footings and foundations are just about finished! So expect to see some steel being delivered soon! Inside the building work has been going on as well. Some of the electrical systems are being put into place, including a new fire alarm system.

Construction is not the only thing happening at the City Center though. In the past few weeks we've hosted the annual Bartenders Ball, Dance Flurry and a Bridal Show. Coming up next- The Rotary Home Show! Stop by this weekend, check out the Home show and the construction progress .

Friday, January 22, 2010

Saratogian Article

Photographer Emily Miller from the Saratogian got some great shots of the construction yesterday, check them out!


And read the article by Patrick Donges here: http://www.saratogian.com/articles/2010/01/22/news/doc4b59156b3ae50015696296.txt

Monday, January 18, 2010

Foundations

Demolition is finally complete! Well, at least is is on the front of the building. The footings are in place and the foundation is ready to be poured.